The First Deck on a New Build in Meridian

Century Farm, Bainbridge and the newer Meridian streets are full of houses with a back door onto bare ground. Six things to settle before the first deck.

Walk any of Meridian’s newer streets, Century Farm in the south, Bainbridge off Chinden, the newer phases of Paramount, and the pattern is identical. A slider or a french door on the back of the house, a step down, and grass. The builder graded the lot, laid sod, and stopped.

That is a deliberate commercial decision, not an oversight, and it means a very large number of Meridian households are planning their first deck from a standing start. Six things are worth working out before anyone quotes.

1. How high the door sits

Measure it. The distance from the door threshold to the finished ground below is the number that shapes the entire project.

Under 30 inches at every point, and no guard is required under the 2018 code Idaho adopted, which removes both the rail cost and a visual barrier between the kitchen and the lawn. Above 30 inches, a guard is required, and the stair run gets long enough to trigger a handrail at four risers.

On many new Meridian builds the door sits somewhere in the twenties, which puts the guard question in play. Stepping the deck down one level from the door to stay under the line is worth pricing even where it seems fussy, because rail is routinely 20 to 30 percent of a budget.

2. Where the easement is

Pull the recorded plat. Meridian subdivision lots typically carry a 10 foot easement across the rear yard, 5 feet along an interior side, and 15 feet on the street side of a corner lot. On a 35 to 45 foot back yard, that removes a meaningful share of the buildable depth, and a structure inside one may have to move at the owner’s expense. Ten minutes now, no redesign later. The easements piece covers where to find it.

3. Which way the yard faces

This decides whether the deck gets used or just gets looked at. NOAA’s Boise normals put the July average high near 93 degrees, and a west-facing yard at 2,600 feet with ten-year-old trees has no shade at all between two and seven in the afternoon.

If the yard faces west or southwest, plan the shade at the same time as the footprint, not two summers later. Retrofitting a cover onto a finished deck means new or enlarged footings under the post positions, because deck footings are sized for people rather than for a roof carrying snow. Framing for a future cover while the deck is open is a modest upcharge; digging under a finished deck is not. The shade guide works through the options.

4. What the settled ground is doing

This is the one specific to new construction. The yard was graded during the build, which means some of what looks like ground is fill. Footings have to bear on undisturbed soil, at least 12 inches down or below the frost line, whichever is deeper, and the frost line governs here. Where there is fill, the excavation has to reach through it, which can mean digging deeper than the 24 inch valley figure.

The building official verifies bearing conditions in the field before concrete is placed and can require a deeper hole on the spot. It is not a problem, but it is a reason a footing quote on a new build should not be treated as a fixed certainty, and a reason to ask how the builder handles it if the hole has to go deeper.

5. Whether the committee needs to see it

Most Meridian subdivisions have an architectural committee, and the newer communities tend to have the most active ones. Submit at the same time as the city permit application rather than after it; two to three weeks of committee turnaround running in parallel costs nothing, and running in series costs a build slot. The committee piece covers what they usually want to see.

6. When to start

Earlier than feels necessary. The Treasure Valley build season runs late March to October and fills from the front, with May and June booking out furthest. Add four to eight weeks of lead-in for design, committee review, permit, and materials, and a call in May is realistically a late-summer deck.

January and February are the right months to start a conversation for a spring build. Nothing happens on site, and everything that has to happen before site work gets done while the calendar is still open. The seasonality guide has the month-by-month picture.

What a first deck usually costs

For a new build in Meridian, the common shapes:

  • 250 square feet, treated, under 30 inches, three steps, no rail: roughly $8,400 to $13,200.
  • 320 square feet, capped composite, guard and a five-riser stair: roughly $25,000 to $44,700.
  • The same with a pergola over the dining zone: add $6,000 to $18,000.

The cost estimator will price your own footprint, and the cost guide explains what moves each line. The one piece of advice that applies to every first deck: size it from the furniture you intend to put on it, not from how big the yard looks from the kitchen window. Yards look bigger empty than they turn out to be.

More field notes

Or work through the longer build guides.

Thinking about a deck this season?

Call (208) 314-4914 or use the quote form for a free written price on any deck project in the Treasure Valley.